Construction update of The Marq project n August 2020

 21 August, 2020

Construction update of The Marq project in August 2020, the structural construction works completed at rooftop floor and the steel structure work is started with Crown supports and swimming pool Capony.

Construction update of The Marq project in August 2020, the structural construction works completed at rooftop floor and the steel structure work is started with Crown supports and swimming pool Capony.

  • Masonry work is underway up to floor 26.

  • Aluminum and glazing works are ongoing to all elevations of building and up to floor 20.

  • Construction of finishing and MEPF works to basement and tower are underway.

Construction Progress of The Marq project is regularly updated at the official website: www.themarq.vn.

Rate this post

Leave a Reply

Your email address will not be published. Required fields are marked *

Is there anything
we can help you with?
Register To Rent
Hotline
(+84)903 188 880
Viber Chat
Zalo Chat
Skype Chat
Whatsapp
Can Ho Cao Cap The Marq Infinity Pool

Get A Quote
THE MARQ DISTRICT 1

     Get The Latest Quote
    vr360