Construction update of The Marq project in August 2020, the structural construction works completed at rooftop floor and the steel structure work is started with Crown supports and swimming pool Capony.

Construction update of The Marq project in August 2020, the structural construction works completed at rooftop floor and the steel structure work is started with Crown supports and swimming pool Capony.

  • Masonry work is underway up to floor 26.

  • Aluminum and glazing works are ongoing to all elevations of building and up to floor 20.

  • Construction of finishing and MEPF works to basement and tower are underway.

Construction Progress of The Marq project is regularly updated at the official website: www.themarq.vn.